Order Production Schedule
|
Our Order No.
|
20151010
|
Client's Order No.
|
14521365
|
Desription of Order
|
BS 1387 Galvanized Pipe in Panama (300 PCS) 42.2*2.65
|
Process steps
|
From date
|
To date
|
Delivery Time
|
Proforma invoice signed
|
2015-10-10
|
2015-10-10
|
-
|
Down payment received date
|
2015-10-12
|
2015-10-12
|
-
|
Feed materials purchasing date
|
2015-10-13
|
2015-10-18
|
7 days
|
Start production
|
2015-10-19
|
2015-11-6
|
18 days
|
Galvanizing
|
2015-11-7
|
2015-11-8
|
2 days
|
Pipe end, marking
|
2015-11-9
|
2015-11-10
|
2 days
|
The third party inspection
|
2015-11-11
|
2015-11-12
|
2 days
|
Total
|
31 days
|