ASTM A53 GR.B SSAW Steel Pipe in MEXICO

Order  Production Schedule
Our Order No.
20150920
Client's Order No.
12548878
Desription of Order
ASTM A53 GR.B SSAW Steel Pipe in MEXICO (1320 Meters) 711.2*8mm
Process steps
From date
To date
Delivery Time
Proforma invoice signed
2015-09-20
2015-09-20
-
Down payment received date
2015-09-22 2015-09-22
-
Feed materials purchasing date
2015-09-23 2015-10-10 18 days
Start production 
2015-10-11 2015-11-02 22 days
Technical operation
2015-11-03 2015-11-05 3 days
Pipe end, marking
2015-11-06 2015-11-08 3 days
The third party inspection
2015-11-09 2015-11-10 2 days
Total 48 days