ASTM A335 P22 Alloy Steel Pipe in Peru

Order  Production Schedule
Our Order No.
20150910
Client's Order No.
10548752
Desription of Order
ASTM A335 P22 Alloy Steel Pipe in Peru (160 PCS) 114-323mm
Process steps
From date
To date
Delivery Time
Proforma invoice signed
2015-09-10
2015-09-10
-
Down payment received date
2015-09-12 2015-09-12
-
Feed materials purchasing date
2015-09-13 2015-09-17 5 days
Start production 
2015-09-18 2015-09-29 12 days
Technical operation
2015-09-30 2015-10-01 2 days
Pipe end, marking
2015-10-02 2015-10-03 2 days
The third party inspection
2015-10-04 2015-10-05 2 days
Total 23 days