ASTM A335 P22 Alloy Steel Pipe in Peru
Putdate:2015-09-12 View(s):1566
Order Production Schedule
|
Our Order No.
|
20150910
|
Client's Order No.
|
10548752
|
Desription of Order
|
ASTM A335 P22 Alloy Steel Pipe in Peru (160 PCS) 114-323mm
|
Process steps
|
From date
|
To date
|
Delivery Time
|
Proforma invoice signed
|
2015-09-10
|
2015-09-10
|
-
|
Down payment received date
|
2015-09-12
|
2015-09-12
|
-
|
Feed materials purchasing date
|
2015-09-13
|
2015-09-17
|
5 days
|
Start production
|
2015-09-18
|
2015-09-29
|
12 days
|
Technical operation
|
2015-09-30
|
2015-10-01
|
2 days
|
Pipe end, marking
|
2015-10-02
|
2015-10-03
|
2 days
|
The third party inspection
|
2015-10-04
|
2015-10-05
|
2 days
|
Total
|
23 days
|