API 5L X52 PSL1 Line Pipe in Congo

Order  Production Schedule
Our Order No.
20150815
Client's Order No.
03234615
Desription of Order
API 5L X52 PSL1 Line Pipe in Congo (1100 MT)16"*9.53&20"*16.6mm
Process steps
From date
To date
Delivery Time
Proforma invoice signed
2015-08-15
2015-08-15
-
Down payment received date
2015-08-17 2015-08-17
-
Feed materials purchasing date
2015-08-18 2015-08-24 7 days
Start production 
2015-08-25 2015-10-10 47 days
Technical operation
2015-10-11 2015-10-16 6 days
Pipe end, marking
2015-10-17 2015-10-19 3 days
The third party inspection
2015-10-20 2015-10-21 2 days
Total 65 days