API 5L L245 Seamless Steel Pipe in UAE

Order  Production Schedule
Our Order No.
20150901
Client's Order No.
05794512
Desription of Order
API 5L L245 Seamless Steel Pipe in UAE(1690 MT) 21.3-406.4mm
Process steps
From date
To date
Delivery Time
Proforma invoice signed
2015-09-01
2015-09-01
-
Down payment received date
2015-09-03 2015-09-03
-
Feed materials purchasing date
2015-09-04 2015-09-25 22days
Start production 
2015-09-26 2015-10-31 36 days
Technical operation
2015-11-01 2015-11-04 4 days
Pipe end, marking
2015-11-05 2015-11-07 3 days
The third party inspection
2015-11-08 2015-11-10 3 days
Total 68 days