API 5L L245 Seamless Steel Pipe in UAE
Putdate:2015-09-02 View(s):1610
Order Production Schedule
|
Our Order No.
|
20150901
|
Client's Order No.
|
05794512
|
Desription of Order
|
API 5L L245 Seamless Steel Pipe in UAE(1690 MT) 21.3-406.4mm
|
Process steps
|
From date
|
To date
|
Delivery Time
|
Proforma invoice signed
|
2015-09-01
|
2015-09-01
|
-
|
Down payment received date
|
2015-09-03
|
2015-09-03
|
-
|
Feed materials purchasing date
|
2015-09-04
|
2015-09-25
|
22days
|
Start production
|
2015-09-26
|
2015-10-31
|
36 days
|
Technical operation
|
2015-11-01
|
2015-11-04
|
4 days
|
Pipe end, marking
|
2015-11-05
|
2015-11-07
|
3 days
|
The third party inspection
|
2015-11-08
|
2015-11-10
|
3 days
|
Total
|
68 days
|